Monday, April 25, 2022

ARBITRATION OF CONSTRUCTION DISPUTE AND MECHANICS LIEN


Tozzi v. McLoughlin Constr. Corp., Date filed: 2022-03-24, Court: Supreme Court, Suffolk, Judge: Justice Christopher Modelewski, Case Number: 615869/2021:

"This is an action sounding in claims for breach of contract, conversion, accounting, fraud, fraud in the inducement, and willful exaggeration of a mechanic’s lien. Plaintiff commenced this action by the filing of a summons and complaint on August 18, 2021. The complaint alleges that defendant McLoughlin Construction Corp. (“MCC”) breached a construction contract for the improvement of real property located at 77 Dune Road, Bridgehampton, New York (the “subject property”). The complaint alleges that plaintiff is a resident of the State of Wyoming and is also the owner of the subject property. The complaint further alleges that plaintiff acquired the subject property “with the intent of demolishing the existing home and constructing a new beach front summer home” (the “project”). The complaint further alleges that MCC and defendant James McLoughlin (“McLoughlin”) made certain representations regarding their skills, expertise, and experience in high-end home building to induce plaintiff to enter into a contract with MCC for the construction of the Project. The complaint further alleges that plaintiff and MCC entered into a contract dated August 2, 2018 for the improvement of the subject property by the construction of a two-story single-family residence (the “contract”). By submissions filed on September 29, 2021, MCC and McLoughlin filed a verified answer, third-party complaint, and moved to compel plaintiff to arbitrate his claims pursuant to §§6.1 and 6.2 of the contract (collectively referred to herein as “the arbitration clause”). MCC and McLoughlin argue that the arbitration clause requires this dispute to be resolved by arbitration pursuant to the American Arbitration Association Construction Industry Arbitration Rules. Plaintiff opposes the motion and argues that the arbitration clause in the contract is unenforceable and void under §399-c of the General Business Law (“GBL 399-c”), that MCC and McLoughlin failed to proceed to mediation, which is a condition precedent to arbitration, and that arbitration should not be compelled because not all claims are arbitrable. MCC and McLoughlin reply.

New York State “has a long and strong public policy favoring arbitration” (Matter of Smith Barney Shearson v. Sacharow, 91 NY2d 39, 49, 666 NYS2d 990 [1997]; see also Matter of Nationwide Gen. Ins. Co. v. Investors Ins. Co. of Am., 37 NY2d 91, 371 NYS2d 463 [1975]). “Any doubts as to whether an issue is arbitrable will be resolved in favor of arbitration” (State of New York v. Philip Morris Inc., 30 Ad3d 26, 813 NYS2d 71 [1st Dept 2006] affd 8 NY3d 574, 838 NYS2d 460 [2007]). CPLR 7501 confers jurisdiction on courts to enforce written arbitration agreements (Crawford v. Merrill Lynch, Pierce, Fenner & Smith, 35 N.Y.2d 291, 299 [1974]; see also Flores v. Lower E. Side Serv. Ctr., Inc., 4 NY3d 363, 370 [2005]). Specifically, a “written agreement to submit any controversy…to arbitration is enforceable without regard to the justiciable character of the controversy and confers jurisdiction on the courts of the state to enforce it and to enter judgment on an award” (CPLR 7501). “Where there is no substantial question whether a valid agreement was made or complied with…the court shall direct the parties to arbitrate” (CPLR 7503; see also Degraw Const. Group, Inc. v. McGowan Builders, Inc., 152 AD3d 567, 58 NYS3d 152 [2d Dept 2017]). The arbitration agreement need not be signed “so long as there is other proof that the parties actually agreed on it” (God’s Battalion of Prayer Pentecostal Church, Inc., v. Miele Associates, LLP, 6 NY3d 371, 374, 812 NYS2d 435 [2006]). On a motion to compel arbitration, it must be determined “in the first instance…whether the parties have agreed to submit their disputes to arbitration and, if so, whether the disputes generally come within the scope of their arbitration agreement” (Matter of Norrtheast & Central Contractors, Inc. v. Quanto Capital, LLC, ___AD3d ___, ___NYS3d ___, 2022 WL 791296, 2022 NY Slip Op 01791 [2d Dept 2022] quoting Revis v. Schwartz, 192 AD3d 127, 140 NYS3d 68 [2d Dept 2020]; see also Degraw Const. Group, Inc. v. McGowan Builders, Inc., supra at 569, 58 NYS3d 152 quoting Sisters of St. John the Baptist, Providence Rest Convent v. Geraghty Constructor, 67 NY2d 997, 998, 502 NYS2d 997 [1986]; Highland HC, LLC v. Scott, 113 AD3d 590, 978 NYS2d 302 [2d Dept 2014]). Indeed, “arbitration is a matter of contract” and an “arbitration clause is a contractual right” (Degraw Const. Group, Inc. v. McGowan Builders, Inc., supra at 569, 58 NYS3d 152). A party to an agreement will not be compelled to arbitrate its dispute with another unless the evidence establishes the parties’ “clear, explicit and unequivocal” agreement to arbitrate (God’s Battalion of Prayer Pentecostal Church, Inc., v. Miele Associates, LLP, 6 NY3d 371, 373, 812 NYS2d 435 [2006]).

In determining the rights and obligations of the parties to a contract, it is well-established that “a written agreement that is complete, clear and unambiguous on its face must be enforced according to the plain meaning of its terms” (Greenfield v. Philles Records 98 NY2d 562, 569, 750 NYS2d 565 [2002]; R/S Assoc. v. N.Y. Job Dev Auth., 98 NY2d 29, 32, 744 NYS2d 358 [2002]). “In construing a contract, one of a court’s goals is to avoid an interpretation that would leave contractual clauses meaningless” (Two Guys from Harrison-N.Y. v. S.F.R. Realty Assoc., 63 NY2d 396, 403, 482 NYS2d 465, 468 [1984]). The aim of the court when interpreting a contract is to arrive at a construction that gives fair meaning to all of its terms and provisions, and to reach a “practical interpretation of the expressions of the parties so that their reasonable expectations will be realized” (see Pellot v. Pellot, 305 AD2d 478, 759 NYS2d 494 [2d Dept 2003]; Gonzalez v. Norrito, 256 AD2d 440, 682 NYS2d 100 [2d Dept 1998]; Joseph v. Creek & Pines, Ltd., 217 AD2d 534, 535, 629 NYS2d 75 [2d Dept], lv denied 89 NY2d 804, 653 NYS2d 543 [1996]; see also Matter of Matco-Norca, Inc., 22 AD3d 495, 802 NYS2d 707 [2d Dept 2005]; Tikotzky v. City of New York, 286 AD2d 493, 729 NYS2d 525 [2d Dept 2001]; Partrick v. Guarniere, 204 AD2d 702, 612 NYS2d 630 [2d Dept], lv denied 84 NY2d 810, 621 NYS2d 519 [1994]). As it is a question of law whether or not a contract is ambiguous (W. W. W. Assoc. v. Giancontieri, 77 NY2d 157, 565 NYS2d 440 [1990]), a court must first determine whether the agreement at issue on its face is reasonably susceptible to more than one interpretation (see Chimart Assoc. v. Paul, 66 NY2d 570, 498 NYS2d 344 [1986]). “If the language of the agreement is free from ambiguity, its meaning may be determined as a matter of law on the basis of the writing alone without resort to extrinsic evidence” (Salerno v. Odoardi, 41 AD3d 574, 575, 838 NYS2d 156 [2d Dept 2007]).

Here, there is no dispute that the contract includes an arbitration clause, which reads, in pertinent part, that

[i]f a dispute arises from or is related to this Agreement or a breach thereof, the parties shall endeavor in good faith to solve the dispute through direct negotiations. The Parties hereto agree in the event of a dispute arising stemming from or relating to this Agreement or a breach thereof, they will submit for resolution their dispute to their named designated private arbitrator…. If a dispute cannot be settled through direct negotiations, the parties agree to endeavor to settle the dispute through mediation administered by a mutually acceptable mediator…. If the dispute is not resolved within 10 days of being submitted to mediation, the parties further agree that the unresolved controversy or claim shall be settled through binding arbitration using the American Arbitration Association Construction Industry Arbitration Rules…. Any arbitration decision and/or award is final and binding and may be enforced in the courts of Suffolk County, New York.

The arbitration clause is clear and unambiguous and no party herein is arguing that the clause contains an ambiguity. Further, the arbitration clause is broadly worded and pertains to all claims arising from or relating to the contract. The Court of Appeals has determined that “an arbitration clause is generally separable from substantive provisions of a contract, so that an agreement to arbitrate is valid even if the substantive provisions of the contract are induced by fraud” (Ferrarella v. Godt, 131 AD3d 563, 566, 15 NYS3d 180 [2d Dept 2015] citing Matter of Weinrott (Carp), 32 NY2d 190, 344 NYS2d 848 [1973]). Thus, as a general rule, the issue of fraud in the inducement should be determined by the arbitrator, except where the arbitration clause specifically excludes fraud in the inducement from the issues to be determined by arbitration” (Anderson St. Realty Corp. v. New Rochelle Revitalization, LLC, 78 AD3d 972, 974, 913 NYS2d 114 [2d Dept 2010] citing GAF Corp. v. Werner, 66 NY2d 97, 105, 495 NYS2d 312 [1985] after remand 115 AD3d 1021 [1986] cert denied 475 US 1083 [1986]). Here, the fraud claims are not specifically excluded from arbitration. Further, fraud claims only affect the validity of the arbitration clause when the fraud relates to the arbitration provision itself. Here, there are no allegations “that the agreement was not the result of an arm’s length negotiation, or that the arbitration clause was inserted into the contract to accomplish a fraudulent scheme” (Ferrarella v. Godt, supra 131 AD3d at 566-67; Anderson St. Realty Corp. v. New Rochelle Revitalization, LLC, supra at 974, 913 NYS2d 114). Based upon the foregoing, the breach of contract, conversion, accounting, and fraud claims are to be determined by the arbitrator. There is no dispute that the mechanic’s lien claim is not arbitrable; such liens falling within the exclusive jurisdiction of the Court (see Lien Law §41). Despite plaintiff’s claims to the contrary, GBL 399-c (1)(a) does not apply herein. That statute defines a consumer as a natural person residing in New York. Plaintiff admits in his complaint that he is a resident and citizen of the state of Wyoming. Therefore, he cannot be considered a consumer subject to the provisions of GBL 399-c, which prohibits arbitration clauses in contracts for the sale or purchase of consumer goods. Due to this finding that the prohibitions of GBL 399-c do not apply, the Court need not reach the issue of whether GBL 399-c is preempted by the Federal Arbitration Act (9 USC §1 et seq.). Further, the argument that MCC was required to engage in mediation as a condition precedent to arbitration and that MCC’s failure to mediate precludes it from compelling arbitration are not issues for this Court to decide. Indeed, the issue of whether plaintiff and/or MCC waived mediation or whether MCC waived arbitration, are procedural questions for the arbitrator to decide under the subject arbitration clause (see Matter of Barbalious v. Exterior Wall Sys., Inc., 14 AD3d 508, 787 NYS2d 715 [2d Dept 2005]; Chain Sales Mktg., Inc. v. Roach, 65 Misc3d 1232 (A), 119 NYS3d 829 [Sup. Ct. Suffolk County 2019]; 33 Calvert Props. LLC v. AMEC LLC, 70 Misc.3d 295, 310, 135 NYS3d 767, 779 (Sup. Ct. Westchester County 2020]). The Court has considered the remaining arguments of plaintiff and finds that they lack merit.

Accordingly, the motion by defendants/third-party plaintiffs McLoughlin Construction Corp. and James McLoughlin is granted except as to the mechanic’s lien claim."


Tuesday, February 23, 2021

EXPIRING MECHANIC'S LIEN


EMERALD SERVS. CORP. v. EMPIRE CORE GROUP LLC, 2021 NY Slip Op 30394 - NY: Supreme Court February 9, 2021:

"As discussed in Aztec Window & Door Mfg., Inc. v. 71 Vill. Rd., LLC, 60 A.D.3d 795, 796 (2d. Dept 2009) "Pursuant to Lien Law § 17, a mechanic's lien expires one year after filing unless an extension is filed with the County Clerk or an action is commenced to foreclose the lien within that time and a notice of pendency is filed in connection therewith (see MCK Bldg. Assoc. v. St. Lawrence Univ., 5 A.D.3d 911, 912). In the event neither of these conditions is accomplished within the statutory period, nor is a further extension of the lien obtained by order of the court, the lien automatically expires by operation of law, becoming a nullity and requiring its discharge (see Matter of Cook v. Carmen S. Pariso, Inc., 287 A.D.2d 208, 211)." As plaintiff did not complete either of said requirements during the statutory period, the statutory period, the Liens have expired by operation of law.

Plaintiff cross-moves seeking an Order allowing plaintiff to file extensions of said mechanic's liens, nunc pro tune. As discussed in Aztec, as plaintiff did not apply for extensions of the Liens within the statutory period, the expiration of same is automatic and this Court lacks the power, in its discretion, to grant plaintiff's motion. Plaintiff further argues that they are entitled to a toll of the relevant statutory timeframes pursuant to Executive Order 202.8, which provides, "In accordance with the directive of the Chief Judge of the State to limit court operations to essential matters during the pendency of the COVID-19 health crisis, any specific time limit for the commencement, filing, or service of any legal action, notice, motion, or other process or proceeding, as prescribed by the procedural laws of the state, including but not limited to the criminal procedure law, the family court act, the civil practice law and rules, the court of claims act, the surrogate's court procedure act, and the uniform court acts, or by any other statute, local law, ordinance, order, rule, or regulation, or part thereof, is hereby tolled from the date of this executive order until April 19, 2020." The Court notes that said Executive Order has been superseded by Executive Order 202.67, which provides "The suspension in Executive Order 202.8, as modified and extended in subsequent Executive Orders, that tolled any specific time limit for the commencement, filing, or service of any legal action, notice, motion, or other process or proceeding as prescribed by the procedural laws of the state, including but not limited to the criminal procedure law, the family court act, the civil practice law and rules, the court of claims act, the surrogate's court procedure act, and the uniform court acts, or by any statute, local law, ordinance, order, rule, or regulation, or part thereof, is hereby continued, as modified by prior executive orders, provided however, for any civil case, such suspension is only effective until November 3, 2020, and after such date any such time limit will no longer be tolled."

As plaintiff filed the instant motion after November 3, 2020, its motion cannot be granted upon said grounds. The Court further notes that plaintiff filed the instant action on June 25, 2020 and failed to file a Notice of Pendency at that time. As such, plaintiff's arguments are without merit."

Thursday, May 16, 2013

MORE ON SUPERSTORM SANDY

And as a follow up to yesterday's post regarding mechanic's liens and out of state contractors, see this link:

NYS DFS - BEWARE OF HOME SCAMS

Wednesday, May 15, 2013

FOREIGN CORPORATIONS DOING BUSINESS IN NEW YORK - LIEN LAW

From a discussion on a listserv.........

A question arose regarding one's client, a foreign corporation. A foreign corporation doesn't necessarily mean a corporation from another country: it means one organized in another state. So despite the GW Bridge, a New Jersey corporation in Fort Lee that travels 10 minutes to do some work on 181st Street in Manhattan is a foreign corporation.

The NYS Attorney General Office has a memo on their website as to the requirement of why foregin corporations that do business in New York need to file an autrhorization, etc. A link to it is here:


An excellent memo and the bottom line, as it states: “The consequence of doing business without authority is that the organization may not affirmatively use New York courts until it obtains authority and pays all arrears in fees, penalties, and taxes.”

I do many consultations with Superstorm Sandy victims. One of the many issues we are now facing is foreign (out of state) contractors who came in and did repair work, charged high prices, etc. Besides all the issues of home improvement licenses, breach of contract, shoddy work, etc., there is one other issue: granted these foreign contractors may not be able to sue for large balances allegedly due because they were not authorized to do business in NY but there is nothing in the Lien Law that prevents them from filing a mechanics lien.

And that’s what we have – homeowners with liens filed from foreign contractors – some of these homeowners are elderly too and get anxious when their mortgage free home has a lien put on it. And removing the lien can take time and run into legal fees, even assuming they are defective on their face.

So although foreign corporations not authorized to do business should not do business in NY – they do.


 


Saturday, November 14, 2009

MECHANIC'S LIEN - A NOTE TO CONTRACTORS AND OTHER SMALL BUSINESS OWNERS

A recent consultation revealed that a licensed contractor had not been paid for work performed on a residential home over two years ago. Contractors and residential owners should be aware of the New York Lien Law:

"New York law permits "A contractor, subcontractor, laborer, materialman, landscape gardener, nurseryman or person or corporation selling fruit or ornamental trees, roses, shrubbery, vines and small fruits, who performs labor or furnishes materials for the improvement of real property with the consent or at the request of the owner thereof, or of his agent, contractor or subcontractor, and any trust fund to which benefits and wage supplements are due or payable for the benefit of such laborers, shall have a lien for the principal and interest, of the value, or the agreed price, of such labor, including benefits and wage supplements due or payable for the benefit of any laborer, or materials upon the real property improved or to be improved and upon such improvement, from the time of filing a notice of such lien..." N.Y. Lien Law §3. "Notice of lien may be filed at anytime during the progress of the work and the furnishing of the materials, or, within eight months after the completion of the contract, or the final performance of the work, or the final furnishing of the materials, dating from the last item of work performed or materials furnished; provided, however, that where the improvement is related to real property improved or to be improved with a single family dwelling, the notice of lien may be filed at any time during the progress of the work and the furnishing of the materials, or, within four months after the completion of the contract, or the final performance of the work, or the final furnishing of the materials, dating from the last item of work performed or materials furnished. N.Y. Lien Law §10. Within five days before or thirty days after filing the notice of lien, the lienor shall serve a copy of such notice upon the owner, if a natural person, (a) by delivering the same to him personally, or if the owner cannot be found, to his agent or attorney, or (b) by leaving it at his last known place of residence in the city or town in which the real property or some part thereof is situated, with a person of suitable age and discretion, or (c) by registered or certified mail addressed to his last known place of residence, or (d) if such owner has no such residence in such city or town, or cannot be found, and he has no agent or attorney, by affixing a copy thereof conspicuously on such property, between the hours of nine o'clock in the forenoon and four o'clock in the afternoon; if the owner be a corporation, said service shall be made (i) by delivering such copy to and leaving the same with the president, vice-president, secretary or clerk to the corporation, the cashier, treasurer or a director or managing agent thereof, personally, within the state, or (ii) if such officer cannot be found within the state by affixing a copy thereof conspicuously on such property between the hours of nine o'clock in the forenoon and four o'clock in the afternoon, or (iii) by registered or certified mail addressed to its last known place of business. Failure to file proof of such a service with the county clerk within thirty-five days after the notice of lien is filed shall terminate the notice as a lien." N.Y. Lien Law §10. Any lien created under New York law shall be a lien for a period longer than one year after the notice of lien has been filed, unless within that time an action is commenced to foreclose the lien, ...." or the appropriate steps are taken to request that the court grant an extension. N.Y. Lien Law §17."

Unfortunately for the contractor and fortunately for the home owner, in the matter before me, the contractor never filed a lien. The residential owner refinanced a new mortgage after the work was completed (which would not have been possible if a lien was filed and foreclosed on). Now the contractor can only sue the owner for the monies due and, if successful, will be a judgment creditor but, to enforce the judgment against the house, upon a sale, can only be paid after the mortgage holder. The construction contract also had no provision for late charges or collection of attorney fees. I point this out as a reminder to small business owners: CONSULT AN ATTORNEY ON MAJOR JOBS AND DON'T DRAFT YOUR OWN CONTRACTS!